Treo @ Kettner Homeowners Assn. v. Superior Court
(2008) 166 Cal.App.4th 1055
COUNSEL
Epsten Grinnell & Howell, Jon H. Epsten and Anne L. Rauch for Petitioner.
No appearance for Respondent. Luce, Forward, Hamilton & Scripps, Charles A. Bird, Valentine S.
Hoy VIII and Anne Morrison Epperly for Real Parties in Interest. OPINION
BENKE, ACTING P. J.-
Petitioner Treo @ Kettner Homeowners Association (Association), a
homeowners association of a condominium project in downtown San Diego,
sued real party in interest Intergulf Construction Corporation,
developer of the project, and other real parties in interest
(collectively Intergulf) for alleged construction defects. A provision
of Association's CC&R's required that all disputes between it and
Intergulf be decided by a general judicial reference pursuant to Code
of Civil Procedure section 638. fn. 1
Intergulf moved for an order submitting the case to a judicial referee.
Association opposed the order, arguing that the provision of its
CC&R's cited by Intergulf was not a contract as required by section
638 and that if it was, it was unconscionable and unenforceable. The
trial court granted Intergulf's motion and ordered the matter to a
general judicial reference. Association petitioned this court for a
writ of mandate, directing the trial court to set aside that order. We
issued an order to show cause.
PROCEDURAL BACKGROUND
Intergulf prepared and on January 12, 2001, recorded a Declaration of
Covenants, Conditions and Restrictions of Treo @ Kettner. The recording
occurred before any purchase agreements were signed. Before the first
close of escrow, Intergulf, on January 8, 2003, recorded an Amended and
Restated Declaration of Covenants, Conditions and Restrictions of Treo
@ Kettner. fn. 2 {Slip Opn. Page 3}
By a complaint dated May 25, 2007, Association sued Intergulf and numerous other entities alleging construction defects.
Citing section 17.4.5 of Association's CC&R's, Intergulf moved for
an Order of General Reference pursuant to section 638. Article 17 of
the CC&R's, entitled "Enforcement," deals both with disputes
between Association and owners of units (owners) and disputes between
Association or owners and Intergulf. The Enforcement sections describe
various nonjudicial procedures for the resolution of disputes. Section
17.4.5 states that if those procedures are unsuccessful, the dispute
shall be resolved by general judicial reference pursuant to section 638.
Association opposed the motion. It argued that the CC&R's, drafted
by Intergulf before Association had an independent board of directors,
was not a contractual waiver of its right to trial by jury as required
by section 638. Association argued that because Intergulf retained no
enforcement rights under the CC&R's, it could not move for a
reference pursuant to section 638. It noted its claims were against not
only Intergulf but also against numerous other entities, none of which
were subject to the claimed reference agreement contained in the
CC&R's. Finally, Association argued that the alleged reference
agreement was unenforceable because it was substantively and
procedurally unconscionable.
The trial court rejected Association's arguments and granted Intergulf's motion for Order of General Reference.
Association petitioned for writ of mandate; we issued an order to show cause.
DISCUSSION
Association argues that its CC&R's are not a contract within the
meaning of section 638, and the trial court erred when it compelled it
to resolve its action against Intergulf by judicial reference.
Association argues that even if its CC&R's are a contract, its
judicial reference provision is unconscionable and unenforceable, and
the trial court erred in concluding to the contrary.
A. Contract Analysis
1. Section 638
Section 638 in relevant part states: "A referee may be appointed upon
the agreement of the parties filed with the clerk, or judge, or entered
in the minutes, or upon the motion of a party to a written contract
or lease that provides that any controversy arising therefrom shall be
heard by a referee if the court finds a reference agreement exists
between the parties." (Italics added.)
In a judicial reference, a pending court action is sent to a referee
for hearing, determination and a report back to the court. A general
reference directs the referee to try all issues in the action. The
hearing is conducted under the rules of evidence applicable to judicial
proceedings. In a general reference, the referee prepares a statement
of decision that stands as the decision of the court and is reviewable
as if the court had rendered it. The primary effect of such a reference
is to require trial by a referee and not by a court or jury. (Trend Homes, Inc. v. Superior Court (2005) 131 Cal.App.4th 950, 955-956.)
2. CC&R's
a. Association's CC&R's
Association's CC&R's are 86 pages long. They deal with a myriad of
matters ranging, for example, from the right of owners to the exclusive
use of their balconies to Association's governance and operation. Most
provisions are mundane. A few relate to Intergulf, its rights and
obligation and its relationship with Association.
Article 17 of the CC&R's deals with their enforcement and with
actions by the Association or an owner against Intergulf. The article
first allows for inspection and corrective action by Intergulf. Any
dispute not so resolved must be submitted to mediation. If mediation
fails, section 17.4.5 of article 17 requires the dispute be resolved by
a general judicial reference.
Section 17.4.6 of article 17 is set out in capital letters and is
entitled, "AGREEMENT TO DISPUTE RESOLUTION; WAIVER OF JURY TRIAL." The
section states Intergulf, and by accepting a deed for Association
property or a condominium, Association and each owner agree to resolve
disputes as required by article 17. In doing so, the section states
Intergulf, Association and owners acknowledge they give up their rights
to have the dispute tried before a jury. The section states that the
dispute resolution system described may not be amended without
Intergulf's written consent.
b. Creation of CC&R's
Among the requirements for the creation by a developer of a common
interest development is the recording of a declaration. (Civ. Code, §
1352, subd. (a).) The declaration includes several
parts, including the "restrictions on the use or enjoyment of any
portion of the common interest development that are intended to be
enforceable equitable servitudes [i.e., CC&R's]." (Civ. Code, §
1353, subd. (a)(1).) The declaration also must provide for and name an
association that will manage the development. (Civ. Code, § 1353, subd.
(a)(1); 1363, subd. (a).) These covenants and restrictions, unless
unreasonable, "inure to the benefit of and bind all owners of the
separate interests in the development." (Civ. Code, § 1354, subd. (a).)
A common interest development is created with the recording of the
declaration, and other required documents, and there is a conveyance of
a separate interest coupled with an interest in the common area or
membership in the association. (Civ. Code, § 1352.) Each owner in a
condominium project is a member of the association. (Civ. Code, § 1358,
subd. (b).)
The developer and any subsequent seller of an interest in a common
interest development must provide a prospective purchaser with, among
other documents, the governing documents of the development including
the CC&R's. (§ 1351, subd. (j); 1368, subd. (a)(1); Bus. &
Prof. Code, § 11018.6, subd. (a).)
3. Equitable Servitudes
Civil Code section 1354, subdivision (a), states that CC&R's "shall
be enforceable equitable servitudes, unless unreasonable, and shall
inure to the benefit of and bind all owners of separate interests in
the development." The section declares that unless the CC&R's state
otherwise, the servitudes may be enforced "by any owner of a separate
interest or by the association, or by both."
In Nahrstedt v. Lakeside Village Condominium Assn. (1994) 8 Cal.4th 361Id. at pp. 370-375.)
our Supreme Court noted the popularity and advantages of common
interest developments and traced the evolution of the legal concepts
that make them possible. It noted that the viability of such shared
ownership communities rests on the existence of extensive reciprocal
equitable servitudes. (
The court stated the declaration in section 1354, subdivision (a), that
CC&R's are enforceable equitable servitudes evidence the
Legislature's intent that recorded use restrictions are to be treated
as such servitudes. The court noted under general law a subsequent
purchaser of land must have actual notice of restrictions; actual
notice is not required to enforce a recorded use restriction covered by
section 1354 against a subsequent purchaser. The inclusion of such
restrictions in the recorded declaration is sufficient notice to permit
their enforcement as equitable servitudes. (Nahrstedt v. Lakeside Village Condominium Assn., supra, 8 Cal.4th at pp. 378-379.)
In Nahrstedt
the court noted that under the law of equitable servitudes courts may
enforce a promise about the use of land even though the person who made
the promise has transferred title to another. The court stated: "The
underlying idea is that a landowner's promise to refrain from
particular conduct pertaining to land creates in the beneficiary of
that promise 'an equitable interest in the land of the promisor.'
[Citations.]" (8 Cal.4th at p. 379.)
The court stated that when the owner of a subdivided tract conveys
parcels with restrictions on each parcel as part of a general plan of
restrictions common to all the parcels and designed for their mutual
benefit, equitable servitudes are created in favor of each parcel and against the others. The court noted that equitable
servitudes permit courts to enforce promises restricting land use when
there is no privity of contract between parties seeking to enforce the
promise and the party resisting enforcement. (Nahrstedt v. Lakeside Village Condominium Assn., supra, 8 Cal.4th at pp. 379-380.)
The court stated: "Like any promise given in exchange for
consideration, an agreement to refrain from a particular use of land is
subject to contract principles, under which courts try to 'effectuate
the legitimate desires of the covenanting parties.' [Citations.]" (Nahrstedt v. Lakeside Village Condominium Assn., supra, 8 Cal.4th at pp. 380-381.)
4. Waiver of Trial by Jury in Civil Cases
As our law has evolved, parties with legal disputes may resolve them in
a variety of ways. They may simply, alone or with the assistance of a
neutral party, agree to settle their dispute. On the other hand, one
party may sue the other with the matter eventually decided in a
courtroom before a jury. Between these two approaches are others that,
while eliminating some or all of the traditional judicial forum,
nonetheless are adversarial and the decision made binding on the
parties, e.g., arbitration and general and special judicial references.
One effect of these devices is that no part of the decision is made by
a jury.
In Grafton Partners v. Superior Court (2005) 36 Cal.4th 944
our Supreme Court discussed the constitutional, statutory and policy
considerations relevant to the waiver of trial by jury in civil cases. Grafton
does not deal, as does this case, with jury waivers resulting from
prelitigation contracts agreeing to general judicial references
pursuant to section 638. It deals rather with
prelitigation contractual waivers of jury trial in the traditional
judicial forum pursuant to Code of Civil Procedure section 631. While
not precisely on point, Grafton, nonetheless, discusses the
policy considerations that underpin any pretrial contractual waiver of
jury trial in civil matters and is useful in reviewing the issues
raised here.
Grafton Partners hired an accounting firm. The engagement letter
confirming the terms of the retainer agreement stated that in the event
of a dispute, the parties, to facilitate judicial resolution and save
time and money, agreed not to demand trial by jury. A dispute arose.
Grafton Partners sued and demanded a jury trial. The issue was whether
the parties' pretrial contractual wavier of trial by jury was
enforceable. (Grafton Partners v. Superior Court, supra, 36 Cal.4th at pp. 950-951.)
The court began by noting that article I, section 16 of the California
Constitution states that trial by jury is " 'an inviolate right' " that
in civil cases may be " 'waived by the consent of the parties expressed as prescribed by statute.' " (Grafton Partners v. Superior Court, supra,
36 Cal.4th at p. 951, fn. 3.) When a party, based on a contract,
asserts that a dispute be decided by some entity other than a jury,
they must identify a statutory basis allowing such waiver and the
consent of the opposing party to so proceed.
The court in Grafton
noted that section 631 provides six means by which trial by jury can be
forfeited or waived in the traditional judicial forum. None of the six
states that jury trial may be waived by prelitigation contract. The
court concluded it was not enough that section 631 did not forbid such
waivers or was it determinative that other statutes allow for
predispute contractual agreements that result in a wavier of trial by jury, e.g., contracts to arbitrate (section 1281)
or submit matters to judicial reference (section 638). (36 Cal.4th at
pp. 951-952, 957.)
In Grafton the court held that the
rules under which the parties to a lawsuit may waive jury trial must be
prescribed by the Legislature and that the power to do so may not be
delegated to the courts. (36 Cal.4th at pp. 952-955.) The court noted
this restriction existed because the right to trial by jury is " 'too
sacred in its character to be frittered away or committed to the
uncontrolled caprice of every judge or magistrate in the State.' " (36
Cal.4th at p. 956, quoting Exline v. Smith (1855) 5 Cal. 112,
113.) The court also noted that the right to trial by jury is
"considered so fundamental that ambiguity in the statute permitting
such waivers must be 'resolved in favor of according to a litigant a
jury trial.' [Citation.]" (Grafton Partners v. Superior Court, supra,
36 Cal.4th at p. 956.) The court noted the right is so important it
must be "'zealously guarded' in the face of a claimed waiver." (Ibid.)
The court observed that doubts in interpreting the waiver provisions of
section 631 had been resolved in favor of a litigant's right to jury
trial. (Id. at pp. 956, 958.)
The court noted that "even those jurisdictions permitting predispute
waiver of the right to jury trial do not uncritically endorse
unregulated freedom of contract; rather, they seek to protect the
constitutional right to jury trial with a number of safeguards not
typical of commercial law, including requirements that the party
seeking to enforce the agreement bear the burden of proving that the
waiver clause was entered into knowingly and voluntarily, restrictions
on the type of contracts that may contain jury waivers, presumptions
against a finding of voluntariness, inquires regarding the parties' representation by counsel as well as relative
bargaining power and sophistication, and consideration of font size and
placement of waiver clause within the contract." (Grafton Partners v. Superior Court, supra, 36 Cal.4th at pp. 965-966.)
5. Discussion
In Villa Milano Homeowners Assn. v. Il Davorge (2000) 84 Cal.App.4th 819, a case decided before Grafton,
the court held that, in the abstract, an arbitration clause contained
in the CC&R's of a condominium homeowners association was a
sufficient agreement within the meaning of sections 1281 and 1281.2 to
require the association's construction defect claims against the
developer be submitted to arbitration. The court, however, found the
agreement unconscionable and unenforceable.
In finding the arbitration clause in the CC&R's a sufficient
agreement to require the matter be submitted to arbitration, the court
noted that individual owners " 'are deemed to intend and agree to be
bound by' " (Villa Milano Homeowners Assn. v. Il Davorge, supra,
84 Cal.App.4th at p. 825) the written and recorded CC&R's inasmuch
as they have constructive notice of the CC&R's when they purchase
their homes. The court stated: "CC&R's have thus been construed as contracts in various circumstances." (Ibid.,
italics added.) The court gave as examples treating the CC&R's as a
contract with respect to the installation of common area lighting, fn. 3 prohibiting the use of a residence for business purposes fn. 4 and for the maintenance and repair of common area plumbing. fn. 5 (Ibid.; see also Sproul & Rosenberry, Advising Cal. Common Interest Communities (Cont.Ed.Bar 2003) §§ 4.74-4.76 [questioning whether CC&R's should be treated as contracts].)
We agree with Villa Milano
insofar as it holds that CC&R's can reasonably be "construed as a
contract" and provide a means for analyzing a controversy arising under
the CC&R's when the issue involved is the operation or governance
of the association or the relationships between owners and between
owners and the association; we do not believe, however, they suffice as
a contract when the issue is the wavier pursuant to section 638 of the
constitutional right to trial by jury.
The question here, as it was in Grafton,
is to ascertain the intention of the Legislature with regard to
prelitigation contractual waiver of the right to trial by jury. When
the Legislature stated in section 638 that the right could be waived by
written contract, did it mean the term contract to include equitable
servitudes created by the CC&R's of common interest communities? We
do not believe that it did.
Section 638 was amended in 1982 to allow parties by written contract or
lease to agree that any controversy arising therefrom be heard by
reference. We have reviewed the legislative history applicable to that
amendment. The amendment was sponsored by the State Bar and was an
attempt to lessen judicial delays that were at the time a serious problem. Nothing in the legislative history, however,
defines or illuminates what the Legislature meant by the term
"contract" or whether an equitable servitude arising from the
CC&R's or a common interest community suffices.
Grafton provides an analysis of the right to trial by jury
anchored in our Constitution and the policy that the right is a
fundamental one and that, while it may be waived, the circumstances and
manner of its waiver are serious matters requiring actual notice and
meaningful reflection. Certainly, the Legislature was concerned with
these considerations in enacting section 638.
The difficulty here is the manner in which the "contract" between
Intergulf and Association waiving the right to trial by jury came
about. As we have noted, an association, with its obligations and
restrictions as defined in the CC&R's, essentially springs into
existence when there is a conveyance by the developer of a separate
interest coupled with an interest in the common area or membership in
the association.
It is at least arguable that there is some meeting of the minds between
the developer and the party to whom the first conveyance is made. The
problem, however, is that later purchasers and their successors, who
will make up almost all association members, effectively have no choice
but to accept the CC&R's prepared by the developer, including in
this case the waiver of the right to trial by jury.
We conclude this is not the situation the Legislature contemplated when
it enacted section 638 to allow parties to waive by contract the
"inviolate" constitutional right to trial by jury. As Grafton
suggests, Legislatures when providing for the contractual waiver of
that right are particularly concerned with the formalities of the
process and the actual existence of a mutual
agreement to waive the right. (See Grafton Partners v. Superior Court, supra, 36 Cal.4th at pp. 956, 958, 965-966.)
Treating CC&R's as a contract such that they are sufficient to
waive the right to trial by jury does not comport with the importance
of the right waived. CC&R's are notoriously lengthy, are adhesive
in nature, are written by developers perhaps years before many owners
buy, and often, as here with regard to the waiver of trial by jury,
cannot be modified by the association. Further, the document is not
signed by the parties.
Treating CC&R's as equitable servitudes makes possible the
existence of common interest communities because they allow the
continued governance of the community when multiple parties own the
property and when such ownership changes over time. The very nature,
however, of the creation of CC&R's creates a distance in time and
control between the parties that are bound by them. While it may be
reasonable under such circumstances to bind owners and the association
concerning the governance of the community and the placement of
restrictions on the use of property, we conclude the Legislature did
not intend that CC&R's be sufficient to effectively and permanently
waive the constitutional right to trial by jury.
We conclude that a developer-written requirement that all disputes
between owners and the developer and disputes between the association
and the developer is not a written contract as the Legislature
contemplated the term in the context of section 638. The trial court
erred in finding to the contrary. Because of this conclusion, it is
unnecessary we reach Association's claim the jury waiver provision is
unconscionable.
DISPOSITION
Let a peremptory writ of mandate issue directing the superior court to
vacate its November 30, 2007, order granting the motion for general
reference and enter an order denying the motion. The stay issued by
this court on February 27, 2008, is vacated. Petitioner is entitled to
costs in the writ proceeding.
McIntyre, J., and Aaron, J., concurred.
FN 1. All further statutory references are to the Code of Civil Procedure unless otherwise specified.
FN 2.
The purchase contracts between Intergulf and the purchasers of
individual units also included judicial reference provisions. Those
provisions are not applicable to the present matter.
FN 3. Frances T. v. Village Green Owners Assn. (1986) 42 Cal.3d 490, 512-513.
FN 4. Barrett v. Dawson (1998) 61 Cal.App.4th 1048, 1054.
FN 5. Franklin v. Marie Antoinette Condominium Owners Assn. (1993) 19 Cal.App.4th 824, 828, 833-934.